The window I stop for is the old one someone is about to burn the paint off.
This talk supplements the site's own risk assessment and method. It does not replace them, and it is not a substitute for competent health and safety advice.
Read this out
This talk is about lead in the paint, the flashings and the old pipework on this job. HSE's construction page on lead says lead is used as a specialist material, for example roof flashings, and it is present in older buildings, for example in paint or pipework. Breathing or ingesting lead dust or fume is the harm. HSE's page says lead can cause serious health problems such as anaemia or kidney disease, and that published research has linked exposure to a small number of occupational cancers. The busy-builder sheet CIS79 says breathing or ingesting lead dust or fume can cause serious problems such as kidney, nerve and brain damage, or infertility. I am using those words. I have not added a count of my own. I read the construction lead page, CIS79 and HSE's lead FAQ on 20 October 2026.
The Control of Lead at Work Regulations 2002 say employers must protect employees against the risks from lead. HSE's model is assess, control, then review. The assessment has to find the tasks that use lead or create lead dust or fume, and pay attention where significant exposure is expected. HSE's list includes stripping or preparing leaded paint on doors, windows and similar; working with lead on roofs; hot cutting of lead or leaded paint in demolition and dismantling; and blast removal of old leaded paint. Lead pigments were widely used in paints for homes, schools and offices until the 1960s. They were not removed from all commonly used paint until the early 1980s. Lead paint can sit underneath the paint you can see, in an older building. CIS79 says you are most at risk if you regularly remove existing paint in properties built before the 1980s, strip old paint with blow lamps or gas torches, or dry sand old paint.
The first control is to stop making the dust and the fume. Where you can, use a different material, or a different method. HSE says leave paint in place when it is in good condition, or when it is covered by paint that does not contain lead. Make a key for the new coat with wet abrasive paper. Only strip old paint if it is flaking, chipping, giving off dust or particles, or it is a risk to children. CIS79 says the same plan in a shorter line: only strip back old paint if it is flaking, chipping, or a risk to children. If the paint is in good condition, wet abrasive paper is the key, not a dry sanding disc. Cold or mechanical cutting comes before hot cutting. Do not overheat leaded paint with a blow lamp or a gas torch. HSE says keep hot air guns and infrared equipment below 500 degrees Celsius. That figure is HSE's. It is not a target to work up to.
If the paint is in poor condition and it has to come off, HSE's methods are a chemical paint stripper, wet abrasive paper and a scraper, on-tool extraction with an H or M class unit, and an infrared tool or a hot air gun used with a scraper, kept below that 500 degree line. CIS79 says use a combination of chemical paint stripper, wet abrasive paper and on-tool extraction, and it says passive capture bags on tools are less effective. A general vacuum is not the unit this page is describing. The silica talk on this site is the one for bricks, concrete and plaster dust. This talk is lead. The extraction class HSE names here is still H or M.
Respiratory protection is often still required. HSE says wear RPE with an assigned protection factor of 20, for example an FFP3 disposable mask or a half mask with a P3 filter. For longer work, consider powered RPE with the same protection, for example a TH2 powered hood or helmet. It has to be compatible with the other kit. Tight-fitting masks need a face-fit test. Stop the dust spreading. HSE says use plastic sheeting to separate the work and cover surfaces, remove or protect soft furnishings, wash the surfaces, and dispose of contaminated waste safely. Pay particular attention to keeping children and pregnant women away from the work area. CIS79 says put debris, cloths and abrasive paper in a plastic bag, and remove debris with a damp cloth. Wear disposable coveralls, and washable gloves such as PVC, or disposable gloves, if lead dust is likely to contaminate them. Take them off when you leave the work area. Do not wear them in the rest area. Keep them away from the clothes you wear home. Avoid washing contaminated clothing at home.
Washing is a control, not a courtesy. HSE says standard site welfare is enough in many cases, and that people should wash hands and forearms before eating, drinking, smoking, using the telephone, or taking medication. Avoid hand-to-mouth contact in the contaminated area. Take breaks away from the work. CIS79 says the small sink is not suitable: provide a large sink, hot or warm running water, and soap. People need to know the coating can contain lead, and how to use the controls. If we do not know whether the old paint contains lead, we treat the stripping, the burning and the dry sanding as this talk until we do know. A photo is not an analysis.
What we do on this job: is the paint staying because it is sound; if it is coming off, are we using wet paper, stripper or H or M class extraction rather than a dry disc or a flame; is the hot air kit below 500 degrees Celsius; who is kept out, including children and anyone who is pregnant; where the waste bag goes; and where people wash their hands and forearms before they eat. If the plan is to burn it off because that is quick, we do not start.
Key points
- Lead is in older paint, in roof flashings, and in old pipework. Pigments were in common paint until the early 1980s, and they can sit under the coat you can see.
- HSE: lead can cause anaemia or kidney disease, and published research has linked exposure to a small number of occupational cancers. CIS79 also names kidney, nerve and brain damage, and infertility, from breathing or ingesting dust or fume.
- Leave sound paint in place and key it with wet abrasive paper. Strip it only if it is flaking, chipping, giving off dust, or a risk to children.
- Do not dry sand old paint. Do not burn it off with a blow lamp or a gas torch. Keep hot air guns and infrared equipment below 500°C.
- Where it has to come off: chemical stripper, wet paper and a scraper, or on-tool extraction with an H or M class unit. Bag the waste. Passive capture bags are less effective.
- RPE with an APF of 20, disposable coveralls, and a wash of hands and forearms before eating, drinking or smoking. Keep children and pregnant women out of the work area.
Questions to ask
- Is this paint sound enough to leave, and key with wet paper, or does it have to come off?
- If it is coming off, what are we using instead of a dry disc or a flame?
- If we are using a hot air gun, how do we know it is staying below 500°C?
- Who is kept out of this room, including children and anyone who is pregnant?
- Where do we wash hands and forearms before anyone eats, and where does the waste bag go?
The sheet below is for this talk. A blank register on its own page is the toolbox talk sign-off sheet.
Attendance and sign-off
Print this sheet for the people who were in the briefing. It is one A4 page on its own when you print the sheet. The whole talk prints with the sheet on a new page. Pop your email in the first time. After that, the buttons print straight away.
Toolbox talk sign-off
Old lead paint
This talk supplements the site's own risk assessment and method. It does not replace them, and it is not a substitute for competent health and safety advice.
- Site or job
- Date
- Supervisor
- Talk started
I was at this briefing and I had the chance to ask a question. Signing does not replace the site risk assessment.
| No. | Name | Trade | Signature |
|---|---|---|---|
| 1 | |||
| 2 | |||
| 3 | |||
| 4 | |||
| 5 | |||
| 6 | |||
| 7 | |||
| 8 | |||
| 9 | |||
| 10 | |||
| 11 | |||
| 12 |
Supervisor signature
Time finished
Sources
Read on 20 October 2026. The links are the pages the talk was taken from. None of them are affiliate links.
- HSE: Lead in construction (opens in a new tab)
- HSE CIS79: Old lead paint, what you need to know as a busy builder (PDF) (opens in a new tab)
- HSE: Lead FAQ, removing old paint (opens in a new tab)
Related: COSHH and hazardous substances, Silica dust, Toolbox talks for painters and decorators.
For your trade: Toolbox talks for plumbers and heating engineers, Toolbox talks for roofers, Toolbox talks for painters and decorators.
RAMS
Free RAMS generator
A talk is the briefing. The RAMS is the plan for the job. I'll turn the work you describe into a risk assessment and method statement you can read on the page.
Open the RAMS generator
Other talks
- Working at height
- Manual handling
- Silica dust
- Slips, trips and falls
- Power tools and hand-arm vibration
- Asbestos awareness
- Using AI tools safely on site
- Working in cold weather
- Working in heat and sun (UV)
- Noise at work
- COSHH and hazardous substances
- PPE
- Ladders and stepladders
- Fire safety and hot works
- Electrical safety
- Mental health and wellbeing
- Lone working
- Driving for work and van safety
- Scaffolding awareness
- Excavations and trenches
- Site housekeeping
- Christmas and new year shutdown
- Roof work and fragile surfaces
- Confined spaces
Free toolbox talk pack
All 25 talks and a blank sign-off sheet, on one page you can print. The talks stay on this site to read. Opening the pack asks for an email the first time, the same as printing a sheet.
Get a ready-to-read toolbox talk every week
I've spent over 20 years in UK construction. Every issue of my free weekly email includes a toolbox talk you can read out on Monday morning, plus plain-English tips for the van and the office.
Free tools for a day rate, a tax estimate, a CIS deduction, and materials are on the tools page.